Official Information Regarding KiwiRail’s Project iReX - Phase 1
2024年5月10日 · KiwiRail’s project to replace the existing Interislander ferry fleet with two large ferries and undertake associated landside redevelopment (Project iReX) is being wound down …
What to expect from today's Interislander announcement
4 天之前 · The next steps for replacing the Interislander ferries will be revealed by Winston Peters today, more than 15 months since the coalition scrapped its predecessor's iReX ferry project. …
KiwiRail's $8m bill for consultants is unacceptable - minister
2 天之前 · KiwiRail's $8 million spend on management consulting is unacceptable, says Minister for Rail Winston Peters. KiwiRail contracted McKinsey and Company on 6 December 2023, for …
Govt's iRex ferry cancellation costed at $300 million — for now
2025年3月4日 · The contract, known as iRex, was cancelled with Hyundai shortly after the coalition came to power, citing a $3 billion cost blowout associated with the ferries and the …
Next step for new generation Interislander ferries - KiwiRail
2020年5月27日 · KiwiRail’s iReX Project was established to replace the existing three ship fleet with two new, large, rail-capable ships to be brought into service during 2024 and 2025. …
KiwiRail statement on Project iReX
2023年12月13日 · The KiwiRail Board was yesterday advised by the Government that it has decided not to provide further funding for the Inter-Island Resilient Connection (iReX) project. …
Through Project iReX, KiwiRail is improving the resilience of the Cook Strait link by replacing its ferry assets. The project requires considerable landside infrastructure development, working …
Govt documents released on KiwiRail’s abandoned iReX project
2024年5月14日 · The iReX project was set to replace Interislander’s three aging Cook Strait vessels with two larger rail-enabled ferries. However, the Government canned the undertaking …
Peters releases details of new Interislander ferries
4 天之前 · Exact cost estimates for iReX vary depending on timings and who you ask. Total project costs at the time the ship contract were signed were about $1.45b, and by the time it …
'Bare-faced lie' to blame me for ferry saga - Winston Peters
3 天之前 · Most of the cost blowout in the iReX plan was due to infrastructure upgrades required to service the larger ships. Speaking to Morning Report on Tuesday, Peters said it was …